Quantum Data Energy (QDE)  has commenced commercial operations at its 5 MW Bordesley flexible generation power project in the UK, marking its third operational asset alongside Pyebridge (8.1 MW) and Hindlip (7.5 MW).

The Bordesley project, fully funded in partnership with Power Balancing Services (PBS), completed construction and commissioning on schedule and within budget. The facility is now generating and trading electricity in the UK wholesale market.

Commissioning involved performance testing of both Caterpillar G3520K generator sets, successful remote start and end-to-end testing with the site's route-to-market provider, and finalisation of operations and maintenance arrangements.

Bordesley previously achieved its Substantial Completion Milestone under its Capacity Market agreement on 30 September 2026, securing a 15-year T-4 Capacity Market contract covering delivery years through 2039/2040.

With Bordesley now operational, QDE has three flexible generation assets with a combined capacity of 20.6 MW.

QDE's CEO Pieter Krügel said: “We are delighted that Bordesley has entered commercial operations, becoming our third operational flexible generation asset, delivered within timeline and budget. We would like to thank everyone involved, especially the teams on site, Power Balancing Services as our partner, and NGED. We look forward to updating the market on Bordesley’s operational performance in due course. In addition to Pyebridge, Hindlip and now Bordesley all generating, QDE is progressing its portfolio of development projects, as well as continually assessing opportunities to acquire existing assets, all of which contribute to our strategy to build a portfolio of 300+ MW of flexible generation assets.”

View from Vox

Bordesley's entry into commercial operations represents another milestone in QDE's portfolio expansion, bringing its operational flexible generation capacity to 20.6 MW. The addition of a third revenue-generating asset, supported by a long-term Capacity Market contract, strengthens the company's operating base as it advances its development pipeline and evaluates acquisitions towards its target of more than 300 MW of flexible generation capacity.